Car battery gigafactory builder drops out
AgratasThe company building the UK's biggest electric vehicle (EV) battery factory has said its opening remains "on track", despite a major contractor stepping away from the project for the second time in six months.
The gigafactory near Bridgwater in Somerset, is being led by Agratas and built on the site of a former ordinance factory, creating around 4,600 jobs once open.
Contractor TSL, which is building the factory's exterior, will step down once that work is complete, but the company has declined to say why and it is unclear if it had planned further involvement.
Buckinghamshire-based TSL only joined the project in June after previous lead contractor Sir Robert McAlpine ended its involvement.
Agratas, part of the Tata Group which owns Jaguar Land Rover, said it will not need to replace TSL as it is already working with another contractor - NG Bailey - who will carry out the remaining work fitting out the inside of the factory.
A spokesperson for Agratas said: "We are on track to meet our customer requirements.
"The Somerset site is a large and complex industrialisation project, and all of our supplier partners are supporting us well as we prepare for the facility's launch phase."
Construction of the factory on the 616 acre (249.2 hectare) brownfield location near Bridgwater was expected to take two years, with about 2,000 people working on site this year.
Project leader Agratas said in the summer the original 2026 factory opening date had been pushed back to 2027, and has now confirmed it will be the end of that year.
The company said 1,500 operational jobs would be created in 2027, with 4,600 jobs on offer once it expands across the whole site.
AgratasFollow BBC Somerset on Facebook and X. Send your story ideas to us on email or via WhatsApp on 0800 313 4630.