Controversial incinerator plans approved on appeal

News imageMVV Environment A computer generated image of an incinerator. The building resembles a factory, with two curved rooftops at its highest point. A long, thin chimney is extending upwards from the left of the building. MVV Environment
The incinerator, shown here in an artist's impression, will be built at Canford Resource Park, off Magna Road, in Poole

Controversial plans to build an incinerator have been approved following an appeal.

The Planning Inspectorate allowed MVV Environment Ltd's appeal over the energy-from-waste facility at Canford Resource Park, off Magna Road, in Poole, on Tuesday, overturning a refusal from Bournemouth, Christchurch and Poole (BCP) Council.

Mid Dorset and North Poole MP Vikki Slade called the decision a "clear step in the wrong direction", while campaigners had raised concerns about the impact on health and the plant's proximity to homes.

However, a planning inspector found there was a need for the plant and that, with safeguards in place, the evidence did not show a significant risk to public health.

The incinerator would burn up to 260,000 tonnes of rubbish that cannot be recycled each year to generate energy.

Its main building would be up to 50m (164ft) high with a 110m (361ft) chimney, and it would run for 40 years before the site is cleared.

BCP Council's planning committee rejected the plans in June 2025, with six of the nine councillors voting against, despite planning officers twice recommending approval.

Residents' campaign group Magwatch had raised concerns about health, the height of the chimney and how close the site was to homes and Canford Heath.

It also argued the plant was not needed because of other proposed facilities at Portland and Parley, but the inspector said those might not be built.

Under the decision, at least 60% of the waste each year must come from a set area, including parts of neighbouring counties, according to the Local Democracy Reporting Service.

Space has been set aside for carbon capture technology, but the inspector said it was unlikely to be in place when the plant opens.

Ward councillors said they were "outraged", while Green Party councillor Alasdair Keedie said he was "devastated".

MVV's managing director Paul Carey said: "We are very pleased with the outcome of our appeal."

He said work to meet the planning conditions needed before construction could begin would start in early 2027.