Flagship £85m road scheme at risk over funding gap
GoogleAn £84.6m scheme to try to solve serious traffic congestion in Coalville could be scrapped because of a shortage of funding.
Leicestershire County Council has been planning the A511 Growth Corridor project since 2019 and had hoped to start work on it early in 2027.
The government has committed more than £40m to the project, which would see part of the road made into a dual carriageway and work to increase the capacity of key junctions in and around the town.
However, officials have warned of an estimated £13m budget gap which it may not be able to plug.
The council's Reform UK cabinet will discuss whether to pause, cancel or press on with the project at a meeting in December.
Supporters of the project have warned it would be "catastrophic" for the town and nearby areas if it were not to proceed.

Amanda Hack, North West Leicestershire's Labour MP, said: "It is really disappointing to see the A511 flagship road scheme facing a funding shortfall.
"Our government has committed around £41m, the majority of the scheme's funding, to support investment in our area.
"Yet now Reform risks turning its back on this vital project after spending nearly £37m in advance debt repayments this year, some of which could have been held back for unforeseen costs and budget shortfalls.
"It raises serious questions about their priorities when major infrastructure investment is being put at risk in the name of savings."
Craig Smith, Conservative councillor for Coalville North, said scrapping the scheme "could not be considered" and traffic on the existing A511 had been "affecting residents for years".
"It would be catastrophic not to go ahead with this," he said.
"The road is already carnage and we are going to get more housing and more industrial development.
"Without this scheme Coalville will come to a standstill."
The council's cabinet member for transport, Andrew Hamilton-Gray, said Smith had his personal support but a decision on whether the scheme would proceed or not would not be taken by him alone.
Supporting growth
The council has already spend £15m on the scheme, acquiring land and doing preliminary work. It had intended to commence the main two-year construction period in March.
Officials said the project would mitigate the impact of a proposed 3,500-home development and major industrial park to the south-east of Coalville.
Under the plans, eight junctions along the stretch of the A511 between the A42 at Ashby and the A50 at Field Head would be remodelled to increase capacity and speed up journey times.
A stretch of the A511 in Coalville between Thornborough Road and Whitwick Road would be dualled, and a new link road would be built at Bardon.
The council said the scheme would cut congestion and pollution in the area and support future economic growth.
While the project has £41.7m of government backing and £29.9m of developer contribution funding, the council said it could struggle to make up the deficit.
The council is facing an £80m deficit in its capital project programme over the next four years.
A county council spokesperson said: "The A511 is an important transport corridor for Leicestershire, linking communities, businesses and strategic routes including the A42 and M1, while supporting future housing and employment growth in North West Leicestershire.
"Work is currently under way to confirm the latest costs and funding position and cabinet will consider proceeding to construction with the full range of evidence, including the wider benefits for Leicestershire, before making the final decision.
"As with all capital schemes of this scale, proceeding is subject to a cabinet decision."
Additional reporting by the Local Democracy Reporting Service
Listen to BBC Radio Leicester on Sounds and follow BBC Leicester on Facebook, on X, or on Instagram. Send your story ideas to eastmidsnews@bbc.co.uk or via WhatsApp on 0808 100 2210.