£9m spent on road widening scheme with no start date

News imageGetty Images A red triangle road sign with a workman shovelling. The word End is underneath. Getty Images
Plans to widen the road were first put forward some 20 years ago

About £9m has been spent developing plans to widen one of Londonderry's busiest roads, despite construction work never beginning.

Proposals to expand the A2 Buncrana Road from two lanes to four were first put forward in 2005.

The Department for Infrastructure (DfI) paused the scheme in 2023, but said at the time it remained committed to the project.

The department has now said it has spent "approximately £9m" on developing the scheme, adding there is currently no estimated start date for work to begin.

The 2.5 mile (4.1km) road runs from Derry's Strand Road to the border with the Republic of Ireland at Bridgend in County Donegal.

As well as doubling the number of lanes, the Buncrana Road plans also include more crossings and a park and ride facility.

The department also said the estimated cost of the scheme had increased from £85m to £100m, adding that figure would need to be reviewed and updated.

Responding to a Freedom of Information request from BBC Radio Foyle's Mark Patterson Show, the department added there was currently no estimated start date, "as the project was being considered as part of its ongoing work on the North West Transport Plan".

The department said the regional transport plan is currently in the technical stage with an initial draft "expected to be available for engagement with key stakeholders towards early 2027, ahead of a public consultation planned for 2027".

News imageMark H Durkan - a man wearing a green corduroy shirt looks at the camera while standing in front of farmland and a body of water.
Mark H Durkan says the amount spent to date is shocking

Foyle SDLP MLA, Mark H Durkan, said the road upgrade remained badly needed and described the £9m spending figure as "shocking".

He said congestion on the Buncrana Road continued to have an impact on commuters and the environment.

Huge government spending on projects with "no tangible progress" has become a depressingly familiar scenario," Durkan said.

While plans may have been first put forward for the road's expansion some 20 years ago, Durkan said the Buncrana Road scheme has been a "a conversation that's been happening for more than 50 years".

"This £9m, I would contend, will be more if we look at what predecessor departments spent prior to 2005 on the project," he told BBC Radio Foyle.

Durkan has written to the Dublin government, as well as DfI minister Liz Kimmins, asking if the Buncrana Road might be funded through the Shared Island Funding scheme.

He said it would be remiss of the Irish government to "plough ahead" with road improvement plans for County Donegal without considering the "linkage to Derry along the north west economic corridor".