Three-year rail safety works begin after landslips
BBCWork has begun on a major project to shore up the walls of a railway cutting after a series of landslips in recent years.
The work at Sonning Cutting in Berkshire, on the Great Western Main Line between London and the West Country and Wales, is expected to continue until early 2030.
Heavy-duty steel mesh will be used to secure the banks of the cutting, held in place by 2m (6ft 7in) long soil nails driven into the clay.
The failures have been linked to changes in the UK's climate, with hotter summers and wetter winters destabilising the Brunel-designed cutting almost two centuries after it was built.
"The last seven years have seen three failures of the cutting," said Network Rail engineer Dan Parkes.
"It's really important for us to keep the railway and passengers safe."
Network RailThe scheme is designed to future proof the cutting for the next 60 years.
Problems here can disrupt trains from Paddington right across the network to Penzance in Cornwall.
Dug by hand in the 1840s, the railway was designed by engineer Isambard Kingdom Brunel.
In recent years, hundreds of sensors have been designed to detect movement in the soil as part of a £1.8m monitoring scheme across the Great Western region.
The system is meant to alert engineers to potential movement in earthworks along the railway, so trains can be brought to a stop until whatever has triggered the alarm is investigated.

Two bridges over the cutting have been closed to traffic during the work.
The one at Butts Hill Road is due to reopen in the New Year, but Warren Road will not reopen until the spring of 2028.
Vegetation has been cleared across much of the site, but larger trees have been left in place.
A survey also found a number of badger setts which ecologists said had been abandoned.
Ayman Aburas, site manager for contractors Taylor Woodrow, pointed out mesh that had been put over the holes in the embankment.
"We're just ensuring the badgers don't come into the vicinity to make another home while we are working," he said.
Science and Society Picture LibraryHeavy rain was an issue for the cutting from the very start.
In December 1841, a train collided with a landslip that had blocked part of the tracks.
Nine people died and 16 others were injured when they were thrown out of the open wagons being used to carry passengers.
Now the railway has turned to 21st Century engineering to try and protect the route for the future.
Matt Malins, project manager for Taylor Woodrow, said about 16,000 steel rods or soil nails would be driven into the embankment to anchor the steel netting.
"They go in almost every part of the cutting about 2m apart," he explained.
"What it does is pin all the soil together, into the embankment, to stop any further collapses."